North America Market Intelligence Briefing

LNG, Data Centre, Semiconductor & Power Sectors

Issue Date: June 30, 2026  ·  Coverage: North America  ·  8 min read

Industrial energy infrastructure at dusk

Overview

Market Pulse

The North American construction landscape is defined by a Gulf Coast LNG mega-wave colliding with an unprecedented AI data-centre and semiconductor buildout. With Corpus Christi Stage 3 nearing full completion, Golden Pass LNG commissioning its first train and beginning Train 2 systems commissioning, and LNG Canada's two trains now both operational and ramping, 2026 marks the inflection point for North American LNG export capacity. Simultaneously, over 670 hyperscale projects are in the global pipeline with approximately 35 GW of capacity currently under construction in North America alone.

670+
Hyperscale Projects in Global Pipeline
35 GW
Data Centre Capacity Under Construction (NA)
$1.15T
Hyperscaler Capex 2025–2027 (Goldman Sachs)
$45.1B/mo
US Data Centre Construction Spend (Dec 2025)

Energy

Key Energy Developments

Corpus Christi Stage 3 (TX)

Trains 5 and 6 reached substantial completion in March and June 2026 respectively. Train 7 commissioning is actively underway — propane introduction approved by FERC in late June — with substantial completion expected August or September 2026. Once complete, the seven-train expansion will add over 10 MTPA to bring Corpus Christi's total capacity above 25 MTPA.

Golden Pass LNG (TX)

Train 1 has shipped three cargoes but remains volatile: feedgas fell near zero on June 29 following flaring issues under investigation with Texas regulators, after peaking at nearly 600 MMcf/d on June 23. FERC approved Train 2 systems commissioning on June 25, 2026. Train 2 first LNG is expected in H1 2027. Train 3 construction and commissioning continues in parallel.

LNG Canada (BC)

Both trains are now operational. Train 1 shipped its first cargo in June 2025 and Train 2 commenced production in November 2025. As of February 2026 the facility had shipped 50 cargoes. FID on Phase 2 — which would double capacity to 28 MTPA — is expected during 2026, with the March 2026 Coastal GasLink cooperation agreement supporting the expansion pipeline case.

DOE Export Approvals

Plaquemines LNG and Elba Island LNG received DOE approval in March and April 2026 to increase permitted exports by 0.5 Bcf/d and 0.1 Bcf/d respectively, expanding the regulatory runway for Gulf Coast export infrastructure.

Industrial

Key Industrial Developments

Data Centre & AI Buildout

Goldman Sachs projects total hyperscaler capex from 2025 through 2027 will reach $1.15 trillion, more than double prior levels. U.S. data centre construction spending reached a monthly rate of $45.1 billion by December 2025, up 85% from two years prior.

Semiconductors & Compute

Elon Musk has proposed “Terafab” centred in Austin, which could ultimately support 1 terawatt of compute capacity annually. TSMC continues its Arizona ramp, with facilities expected to create 6,000 direct jobs alongside wider construction and supply chain employment.

Capital Power Genesee (AB)

The Government of Canada relaxed environmental standards paving the way for Capital Power to expand its 1,857 MW Genesee site, which could accommodate a 1,000 MW, 1-million-square-foot hyperscale data centre.

Contracts

EPC & Contract Awards

Darlington SMR Supply Chain

  • Walters Group — $44.5M structural steel award
  • Marmon Industrial Water — $17.8M condensate purification package
  • Tractel — $9.9M reactor building weather enclosure

LNG EPC

  • McDermott is executing Woodfibre LNG, one of the company's most significant onshore energy projects in North America, with an EPC value exceeding USD 500M.
  • Bechtel remains the lead LNG EPC globally, having delivered or actively executing Sabine Pass, Corpus Christi Stages 3 & 4, Driftwood, Rio Grande, and Port Arthur LNG.

New Entries

New Projects to Track

Alaska LNG (Glenfarne)

Proposed 20 Mt/y export plant in Nikiski. Pipeline FID anticipated late 2025 remains pending. Glenfarne has enlisted Worley ahead of the FID. One to watch as U.S. export policy continues to favour new capacity.

Penzance High Impact Intelligence Center (WV)

$4 billion campus in Berkeley County, West Virginia, delivering 600 MW of IT capacity.

Rio Bravo Pipeline (TX)

138-mile pipeline with capacity up to 4.5 Bcf/d delivering feedgas to NextDecade's Rio Grande LNG terminal.

Williams Southeast Supply Enhancement (VA)

1.6 Bcf/d expansion of the Transcontinental Pipeline expected online in 2027, underpinning feedgas supply to Gulf Coast and Southeast demand centres.

Corpus Christi Stage 4 (TX)

Cheniere filed a FERC application in February 2026 for four large-scale trains adding ~24 MTPA. First commissioning is estimated early 2032. Represents the next major EPC wave at the Corpus Christi complex.

Briefing reflects sources current to June 30, 2026. Golden Pass Train 1 ramp-up remains volatile — recommend validating feedgas and commissioning status directly with site teams before engagement.

About Arbiter

Where Arbiter Fits In

Every project listed in this briefing shares a common challenge: keeping complex, multi-discipline scopes organised, accountable, and on track from first construction activity through to final handover. That's exactly where Arbiter operates. As project scale and complexity grows across LNG facilities, data centres, semiconductor fabs, pipelines, power generation, and nuclear, the demand for structured, software-driven project controls has never been higher.

Construction Controls

Arbiter tracks every punch item, ITR, and work package from first-fix through mechanical completion, giving project teams a single source of truth across multi-discipline scopes.

Pre-Commissioning & Commissioning

Structured subsystem walkdowns, loop checks, and energisation sequencing managed in one platform — reducing rework and keeping complex systems aligned to schedule.

Handover & Turnover

Automated, auditable handover documentation reduces the time and risk of transferring complex facilities to operations, regardless of sector or project size.

How Arbiter Applies Across This Briefing

Project TypeArbiter Application
LNG FacilitiesGolden Pass, Corpus Christi, Woodfibre, Cedar, Port Arthur, Rio GrandeMulti-discipline handover packages; punch and ITR management across large piping, rotating equipment, and controls scopes; train-by-train commissioning progress tracking; regulatory closeout documentation.
Data Centres & Semiconductor FabsTerafab, TSMC Arizona, PenzanceCommissioning management for electrical, mechanical, and controls systems across multiple halls and phases; structured ITR workflows; live C&E tracking.
Nuclear & PowerDarlington SMR, TerraPower Natrium, Capital Power GeneseeSafety-critical ITR control; system-by-system energisation tracking; interface management between EPCs and owner operators; licence-to-operate documentation support.
Pipelines & Gas InfrastructureRio Bravo, Williams Southeast, Commonwealth LNGConstruction completion tracking for linear scopes; hydro-test and pre-commissioning records; streamlined handover packages for operations teams.

As North America's project pipeline accelerates through 2026–2027, owners and EPCs are under increasing pressure to deliver on schedule across some of the most complex capital projects ever built. Arbiter provides the project controls software infrastructure that turns complexity into a controlled, transparent process — from first construction activity through to final handover.

Ready to see Arbiter in action?
Arrange a platform walkthrough tailored to your project type and scope.
Schedule a Demo

This briefing is prepared by Arbiter Completions & Controls for internal and client use. Information is compiled from publicly available sources as at June 30, 2026 and is provided for situational awareness purposes only.